The Ministry of Irrigation and Water Resources will finalize by October digging 26 water wells out of total 50 wells within the framework of the 1.5 million feddan project.
In statements Saturday, Irrigation Minister Hossam Moghazi said the 26 water wells' cost stood at 25 million EGP.
Some 52 water wells dug in 2003 were restored to help reclaim 10,000 feddans within the framework of the 1.5 million feddan project.
The project will include integrated agricultural urban communities and agricultural industrialization zones.
Underground water will supply 80 percent of what is used for irrigation. The remaining 20 percent will come from the Nile River.
GMT 14:03 2018 Thursday ,13 December
Ports of Lattakia, Tartous re-opened for maritime navigationGMT 13:35 2018 Tuesday ,11 December
Harbors in Lattakia and Tartous closed due to weather conditionsGMT 12:42 2018 Wednesday ,14 November
Kuwait suspends work at institutions, schools due to unstable weatherGMT 17:12 2018 Tuesday ,13 November
Jordan flood toll rises to 13 as girl’s body foundGMT 10:13 2018 Tuesday ,06 November
Heavy rains flood Kuwait, public holiday announcedGMT 18:37 2018 Wednesday ,31 October
Egyptian pollution plan signals the last straw cloudGMT 12:54 2018 Tuesday ,30 October
Rains to clear within 48 hours in SharjahGMT 07:56 2018 Friday ,26 October
At least 18 school children die in Jordan flash floodMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor