Aswan High Dam Board Chairman Engineer Mohammad Abdel Moniem Shehata said precautionary measures have been taken to secure the dam's facilities and Aswan reservoir and face any unexpected rise in the River Nile levels at Nasser Lake behind the dam's body.
In statements on Monday, Shehata said there are no risks facing the dam's structure as preparations for the flooding season started in August and will continue till November.
Toskha reservoir has been prepared for receiving any surplus in water levels as it had been constructed to contain 340 million cubic meters of water along with other spillways that could receive about 60 billion cubic meters of water
GMT 14:03 2018 Thursday ,13 December
Ports of Lattakia, Tartous re-opened for maritime navigationGMT 13:35 2018 Tuesday ,11 December
Harbors in Lattakia and Tartous closed due to weather conditionsGMT 12:42 2018 Wednesday ,14 November
Kuwait suspends work at institutions, schools due to unstable weatherGMT 17:12 2018 Tuesday ,13 November
Jordan flood toll rises to 13 as girl’s body foundGMT 10:13 2018 Tuesday ,06 November
Heavy rains flood Kuwait, public holiday announcedGMT 18:37 2018 Wednesday ,31 October
Egyptian pollution plan signals the last straw cloudGMT 12:54 2018 Tuesday ,30 October
Rains to clear within 48 hours in SharjahGMT 07:56 2018 Friday ,26 October
At least 18 school children die in Jordan flash floodMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor