Welded tanks are seen being built above ground at Fukushima nuclear plant
Japan's nuclear regulator on Monday approved a plan to freeze the soil under the crippled Fukushima nuclear plant to try to slow the build-up of radioactive water, officials said. The Nuclear Regulation Authority examined plans
by Tokyo Electric Power Co (TEPCO) to construct an underground ice wall at the Fukushima Daiichi nuclear plant starting in June, regulatory officials said.
The wall is intended to block groundwater from nearby hillsides that has been flowing under the plant and mixing with polluted water used to cool reactors that went into meltdown after an earthquake and tsunami in March 2011.
Under the plan, which is funded by the government, the firm will circulate a special refrigerant through pipes in the soil to create the 1.5-kilometre (0.9-mile)frozen wall that will stem the inflow of groundwater.
"We had some concerns, including the possibility that part of the ground could sink," one official said on condition of anonymity.
"But there were no major objections to the project during the meeting, and we concluded that TEPCO can go ahead with at least part of the project as proposed after going through further necessary procedures."
However, TEPCO may have to review other parts of the project amid fears it might affect existing structures at the plant such as underground drains, he added.
The idea of freezing a section of the ground, which was proposed for Fukushima last year, has previously been used in the construction of tunnels near watercourses.
However, scientists point out that it has not been done on this scale before nor for the proposed length of time.
Coping with the huge -- and growing -- amount of water at the tsunami-damaged plant is proving to be one of the biggest challenges for TEPCO, as it tries to clean up the mess after the worst nuclear disaster in a generation.
As well as all the water used to keep broken reactors cool, the utility must also deal with the water that makes its way along subterranean watercourses from mountainsides to the sea.
Last week TEPCO began a bypass system that diverts groundwater into the sea to try to reduce the volume of contaminated water.
Full decommissioning of the plant at Fukushima is expected to take several decades. An area around the plant remains out of bounds and experts warn that some settlements may have to be abandoned because of high levels of radiation.
Source: AFP
GMT 13:52 2018 Wednesday ,12 December
Expansion of Russia’s presence in Arctic should not do harm to environment, says PMGMT 16:05 2018 Monday ,03 December
Germany diesel crisis: Nearly a billion euros extra for cleaner airGMT 09:08 2018 Tuesday ,27 November
Rare Atlantic walruses spotted in White Sea for first time in several hundred yearsGMT 13:33 2018 Tuesday ,20 November
Environmental Conference: “a crime against the environment is a crime against a human being”GMT 13:11 2018 Thursday ,15 November
NCM warns of rough seas in Arabian GulfGMT 07:48 2018 Monday ,12 November
Northern California fire deaths reach 29, equalling deadliest blazeGMT 14:46 2018 Friday ,02 November
Tanzania launches crackdown on illegal fishing in Lake TanganyikaGMT 08:00 2018 Sunday ,28 October
Environmentalists block mining at controversial German coal site at Hambacher ForestMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor