Up to 216.5 million cubic meters of digging have been completed so far in the Suez Canal Development Project, said Chairman of the Armed Forces Engineering Authority Major General Kamel el Wazir.
The dry digging works will be finalized on April 6 instead of May 6, he added in press statements to MENA on Monday.
The daily digging rate stands at about 500 million cubic meters, he said.
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
It is also projected to become a global hub due to its logistics and industrial services.
The project was funded through granting investment certificates to Egyptians with 12% returns, and in eight days, more than 60 billion pounds were collected.
Source: MENA
GMT 20:32 2018 Friday ,30 November
Turkey hails China's 1st import expo, gets ready for next sessionGMT 17:22 2018 Friday ,26 October
US Trade and Development Agency official meets with ministers in EgyptGMT 11:56 2018 Wednesday ,17 January
BlackRock chief calls on CEOsGMT 12:01 2018 Wednesday ,03 January
Banks 'reticent' to work with SudanGMT 18:43 2017 Thursday ,28 December
Al-Sukait Tackles Investors’ ContributionGMT 18:34 2017 Wednesday ,27 December
Shaath reveals opening date of Metro third lineGMT 07:25 2017 Wednesday ,06 December
Abdelkader underlined role of construction sectorGMT 07:15 2017 Thursday ,09 November
Al Walwel says Palestinian people ableMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor